【单选题】\tBased on the net present value(NPV),which project you will choose ?()\tThe NPV of project A:$25000,project B:$65000,project C://$40000,project D://$35000.
【单选题】The project manager leads a development project for the customer.The project is externally funded with a strict payment plan and deadline.During the project execution phase,the project manager identif...
A.
Perform schedule compression to reach the determined deadline.
B.
Issue a change request and approve it with the customer.
C.
Take no action,since the contract does not identify penalties for late product deliverables.
D.
Decrease the number of quality audit to make the delivery on tim