What is the purpose of the work breakdown structure (WBS)?
A.
The WBS allows the project manager to delegate responsibility of all of the project activities
B.
The WBS is a narrative description of the work required for the project
C.
The WBS describes the total program as a summation of subdivided elements
D.
The WBS is a statement of what will be made, how many units will be made, and when they will be made