【单选题】The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If...
A.
the project is ahead of its planned schedule
B.
less work was completed than was planned
C.
the cost overrun for work completed
D.
the cost under-run of performance to date