【单选题】During the execution phase of the project, you realized the subcontractors are working with incomplete and different scope statements. As the project manager, what should you do FIRST?
A.
Check the work completed against the correct scope statements。
B.
Review the scope of work with the stakeholders。
C.
Document the inconsistencies to management,calculating the cost of non-conformance
D.
Stop all activities until the scope of work is complete。