Adam has a contract with Colin. Four weeks prior to the agreed completion date, Colin telephone's Adam out of courtesy to say he has double-booked and will be unable to carry out the work as agreed.Which of the following statements is true?
A.
Colin has committed an actual breach of contract
B.
Colin has committed an express anticipatory breach of contract
C.
Colin has committed an implied anticipatory breach of contract
D.
Colin has not committed a breach of contract