【单选题】The project manager is reorganizing a team to develop a new product.The company’s technology experts reviewed the standard,and expresses concern that the quality of the product can only be test the ne...
A.
Review project management plan to reflect delays to the schedule and budget.
B.
Inform stakeholders and definite this polential delay.
C.
Update project schedule to account for possible delays.
D.
Update the risk register,which contain the acceptance testing and mitigation plan.