在某工程网络计划中,已知工作 M 的总时差和自由时差分别为5 天和 4 天,监理工程师检查实际进度时,发现该工作的持续时间延长了7 天,说明此时工作 M 的实际进度将其紧后工作的最早开始时间推迟 ( ) 。
A.
7 天,但不影响总工期
B.
5天,但不影响总工期
C.
3 天,并使总工期延长2 天
D.
4 天,并使总工期延长 2 天
拍照语音搜题,微信中搜索"皮皮学"使用
参考答案:
参考解析:
知识点:
皮皮学刷刷变学霸
举一反三
【简答题】Complete the following sentences with an appropriate word or phrase. 1) Young as she is, Mary is very good at h_____ difficult customers. 2) After explaining his plan in great detail, Bob s_____ its m...
【简答题】This study, conducted by Dr. Mary Joe Bane, yzes 1 and 2 about the American family. Dr. Bane expected to prove that the American family was 3 and needed to 4 . But instead, sh...
【简答题】c ompetent, able & capable 1. A ________ mechanic should be able to fix the problem. 2. She was widely regarded as one of the most ________ members of the president's staff. 3. He is ________ of runni...
【简答题】Complete the following sentences with an appropriate word or phrase. 1) Young as she is, Mary is very good at h_____ difficult customers. 2) After explaining his plan in great detail, Bob s_____ its m...
【简答题】I. Fill in the missing words according to the meaning of the sentences. 1. Kate is very s________. She knows how to make a learning plan for herself every year 2. As we all know, c__________ is very i...