When the calculated duration of the project network plan is greater than the required duration, the basic method to optimize the construction duration to meet the required duration is ( ).
A.
Reduce the time interval between adjacent works
B.
Compress the key work duration
C.
Compress the non key work duration
D.
Compress the key work total float