【单选题】During project closure a project sponsor complains that the project did not increase the department's knowledge of Java programming and therefore, the project is not complete . The customer has accept...
A.
begin project closure .
B.
re-plan the project to include the new objective .
C.
meet with the team to discuss the find a resolution .
D.
get the project stakeholders involved to help resolve the issue .