A project team has completed all the technical project deliverables, and the customer has accepted the deliverables . However, the lessons learned required by the project office have not been completed . What is the status of the project?
A.
The project is incomplete because the project needs to be re-planned .
B.
The project is incomplete until all deliverables are complete and accepted .
C.
The project is complete because the customer has accepted the deliverables .
D.
The project is complete because the project has reached the due date .