【单选题】The project manager establishes a risk models that will be used on the Boston project. The risk model shows the risk events and provides the probabilities of occurrence What is missing from this risk ...
A.
Nothing, the risk design is complete
B.
The risk probabilities need to be summed to determine the total project risk
C.
The risk events must be labeled as internal or external risk events
D.
The risk events do not address the technology used by the Boston project
E.
The impact of the risk on the project’s objectives has not been assessed and assigned