皮皮学,免费搜题
登录
搜题
【多选题】
Public administration is defined as()
A.
Public administration houses the implementation of governmentpolicy and an academic discipline that studies this implementation and thatprepares civil servants for this work.
B.
field of inquiry with a diverse scope" its"fundamental goal... is to advance management  and policiesso that government can function.
C.
the study of government decision making, the analysis of thepolicies themselves, the various inputs that have produced them, and the inputsnecessary to produce alternative policies.
D.
PA includes Legislative activities, taxation, national defense,public order and safety, immigration services, foreign affairs andinternational assistance, and the administration of government programs areactivities that are purely governmental in nature.
拍照语音搜题,微信中搜索"皮皮学"使用
参考答案:
参考解析:
知识点:
.
..
皮皮学刷刷变学霸
举一反三
【简答题】两个相邻施工过程(专业队组)先后进入第一施工段的时间间隔,称作()。 A.流水节拍 B.流水施工 C.流水步距 D.流水段
【判断题】当某项工作的拖延超过了它拥有的总时差,就必然造成紧后工作最早开始时间的延误。( )
A.
正确
B.
错误
【单选题】一个双代号网络计划,某工作有3天总时差,若该工作实际施工时间拖延了4天,则计划工期将拖延( )天。
A.
1
B.
2
C.
3
D.
4
【单选题】已知一批独立随机样本服从正态分布,要检验这批随机样本的均值是否与某总体分布的均值相同,则需要采用:
A.
单样本 t 检验
B.
两独立样本 t 检验
C.
S 检验
D.
Q 检验
【单选题】审计人员在执行工程项目跟踪审计时,发现某项工作进度拖延(用△表示此项工作拖延的时间),审核发现该项工作的拖延,对后续工作产生了影响,但并不影响总工期。审计分析该项工作的拖延与总时差和自由时差的关系( )。
A.
FF
B.
TF
C.
△=0
D.
总时差和自由时差无关
【单选题】在双代号网络图中,某工作拖延的时间超过了该工作总时差,则该拖延将会导致( )
A.
紧后工作开始时间拖延,但总工期不变;
B.
紧后工作自由时差减小,但总工期不变
C.
总工期延长
D.
总工期延长,但关键线路不变
【简答题】两个相邻施工过程(专业队组)先后进入第一施工段施工的时间间隔,称作 。
【单选题】已知一批独立随机样本服从正态分布,要检验这批随机样本的均值是否与某总体分布的均值是否存在差异,则需要采用:
A.
单样本 t 检验
B.
两独立样本 t 检验
C.
S 检验
D.
Q 检验
【单选题】两个相邻施工过程的专业队组先后进入第一施工段的时间间隔称作_____。
A.
流水节拍
B.
流水施工
C.
流水步距
D.
流水段
【单选题】单肢箍箍了( )根纵筋
A.
B.
C.
D.
相关题目: