Frank’s Fine Floats is in the business of building elaborate parade floats. Frank and his crew have a new float to build and want to use PERT/CPM to help them manage the project . Answer the following questions: 1, How long it will take to complete the project? 2, What are the scheduled start and completion times for each activity? 3, What activities are in the critical path? 4, How long can non-critical activities be delayed before they cause a delay in the project's completion time, i.e. what are their slacks? Please fill in the table below and upload the scanned results.