【单选题】We have two projects that both require an initial investment of $5,000. The future revenues of project A in the coming 3 years are relatively $1,000, $1,000, $6,000. The future revenues of B are $3,00...
A.
Project A: $-629.60; Project B: $-303.53
B.
Project A: $1243.43; Project B: $ 1709.24
C.
Project A: $1243.43; Project B: $-303.53
D.
Project A: $-629.60; Project B: $1709.24