I worried about my personal image and how I could be remembered during my boyhood.In the fifth grade,there seemed to be only one 1 —to be cool.In the sixth grade,suddenly,there were two choices:be cool,or be invisible. 2 ,one day,when a teacher had us fill out a questionnaire with 3 questions,I found the 4 option. Assuming(假定)the teacher would read our answers privately,I felt it was 5 to share my privacy.To my 6 ,she collected and redistributed(重新分发)them to us.We were asked to 7 the name and our three favorite answers to the whole class.My answers went to the meanest boy in class. The first question was“What's your favorite movie?” My answer was Beauty and the Beast.A laugh erupted and my cheeks 8 .The next was“Where would you like to travel?” My answer was 9 special—“Wherever a book takes me.”The 10 this time had an explosive quality. I could 11 remember what happened next;all that I had in mind was the laughter.But something amazing happened.A(n) 12 came,“Guys,cut it out.”The room went 13 .It's Michelle Siever,a popular and cool girl.Then she 14 ,“Why are you laughing? What is the point of 15 if we just laugh at others?” I can't remember the teacher or other kids' names,but I remember Michelle's.When she 16 for me that day,she 17 me we actually have three choices if we want to be remembered. Be cool,and you might be remembered 18 .Stay invisible,and you won't be remembered at all.But if you stand up 19 someone when he or she 20 you most,then you will be remembered as their hero for the rest of their life.
拍照语音搜题,微信中搜索"皮皮学"使用
参考答案:
参考解析:
知识点:
.
..
皮皮学刷刷变学霸
举一反三
【单选题】组织等节拍流水施工的前提是
A.
各施工过程施工班组人数相等
B.
各施工过程的施工段数目相等
C.
各流水组的工期相等
D.
各施工过程在各段的持续时间相等
【单选题】组织等节 拍 流水施工的前提是 ( ) 相等。
A.
各流水组的工期
B.
各施工过程施工班组人数
C.
各施工过程的 施工段数目
D.
各施工过程在各段 上 的持续时间
【多选题】零售要素组合的各种要素包括( )等
A.
商品
B.
价格
C.
顾客服务
D.
广告及促销
E.
店铺设计与商品陈列
F.
销售、选址
【单选题】组织固定节拍流水施工的前提条件是( )
A.
各施工段的工期相等
B.
各施工段的施工过程数相等
C.
各施工过程施工队人数相等
D.
所有施工过程在所有施工段上的持续时间相等
【简答题】零售要素组合的各种要素包括:商品、价格、顾客服务、广告与促销、店铺设计与商品陈列、销售和()。
【单选题】组织等节奏流水,首要的前提是( )。
A.
使各施工段的工程量基本相等
B.
确定主导施工过程的流水节拍
C.
使各施工过程的流水步距相等
D.
调节各施工队的人数
【简答题】IEEE802.3标准使用一种简易的命名方法,代表各种类型的以太网。以100BaseT为例:100表示数据传输速率为100( )。
【简答题】{一} IEEE802.3标准使用一种简易的命名方法,代表各种类型的以太网。以100 Base T为例:100表示数据传输速率为100()。
【单选题】有节奏流水施工的类型中,()是指在组织异节奏流水施工时,每个施工过程成立一个专业工作队,由其完成各施工段任务的流水施工。
A.
等节奏流水施工
B.
异步距异节奏流水施工
C.
等步距异节奏流水施工
D.
有提前插入时间的固定节拍流水施工